DEPARTMENTS: NOTABLE & NEWSWORTHY

    Two Monopile Handling Innovations Boost Baltic Power Offshore Wind Farm

    06/25/2026
    Two Monopile Handling Innovations Boost Baltic Power Offshore Wind Farm

    ­As wind farms become more globalized and suitable sites are being taken up, so turbines are being built further out to sea. The impact of this is that their foundations’ diameters and heights are increasing to stand up to, and harness, the full force of stronger winds.

    Their weights and sizes are also therefore ever increasing, so the capacity of the equipment used for lifting, transport and installation must grow with them.
     
    Over recent years, Mammoet’s innovations team have been hard at work developing new solutions to deal with the complexities this creates.
     
    Mammoet’s XXL monopile transport system, which debuted in 2024, allows the world’s largest and heaviest monopiles to be marshalled, stored and transported safely - even as they grow at unprecedented rates.
     
    The new MTC 1600 - on site for the first time - is a terminal crane with 1,600t lift capacity. It works in tandem with another unit to lift XXL monopiles safely and efficiently, creating a production line environment.
     
    Both innovations demonstrated their advantages when Mammoet supported Van Oord to marshal over 70 monopiles for Baltic Power offshore wind farm, which will deliver 4TWh of electricity annually – enough to cover 3% of Poland’s national demand.

    Innovative tools to support the future of offshore wind
     
    Mammoet assisted with the lifting and marshalling of 78 monopiles between factory and foundation. The monopiles weighed up to 1,680t, with a maximum of 86.3m in length and a diameter of 9.1m.
     
    The monopiles were shipped in batches of three, via barge, to the Port of Ronne, Denmark. They were initially unloaded using 78 axle lines of SPMT, fitted with Mammoet’s XXL monopile transport system.
     
    When the SPMT combination was in position, the system’s saddles unfolded hydraulically to cradle each monopile. Using the combined stroke of the SPMT and the system’s jacking spacers, the components were safely lifted off the grillages that supported them during sea transit.
     
    They were then driven to a temporary storage location where they were placed on gravel bunds. The jacking spacers were extended fully to allow the monopiles to be lifted an extra 0.6m.
     
    This extra stroke length allows the XXL monopiles to be placed into the bunds and retrieved from them. This is despite the greater lift distance needed to do so caused by the growing indents required to support larger monopiles.
     
    The system’s foldable saddles also allow the height of the bunds to be lower and their lengths shorter – meaning far less gravel is needed, which reduces the amount of civil preparation work necessary on site.
     
    Before load-out, the monopiles were lifted off the storage bunds and taken to a plugging station where they could be plugged at both ends and tested to ensure they were airtight.
     
    They were then driven to the quayside, where the two MTC 1600 cranes effortlessly lifted them into the water – ready to be sailed out to Van Oord’s heavy lift installation vessel, Svanen, using a tug. The foundations ultimately travelled 23km offshore the Polish settlements of Choczewo and Łeba, for installation.
     
    In this fashion, the MTC 1600 is able to turn any quay into an efficient heavy lift terminal for monopile load-ins and load-outs.
     
    In addition to monopiles, Mammoet also marshalled transition pieces for the project in the same port. This followed a similar procedure, except the components were lifted and placed onto SPMTs using an LR1800 crawler crane.
     
    This work comes after Mammoet’s 2024 project to support Van Oord with the upgrade of the Svanen – fitting this vessel with a new A-Frame to install taller monopile foundations at sea for Baltic Power. The refit and this marshaling project are inextricably linked.
     
    Jaap van der Riet, Commercial Manager at Mammoet, explains:
     
    “When we were in discussions with Van Oord, it wanted to upgrade the Svanen to have a 3,000t lifting capacity, so the vessel could install XXL monopiles in the Baltics.
     
    To further support that, we said we would develop cranes and systems that matched this capacity. This is a real strength of Mammoet: if no solutions exist, we develop them, together with our clients, to meet their specific needs”.
     
    Finding efficiencies at every stage
     
    Load testing for the MTC 1600 cranes was carried out at the project site. The load-testing took place at a less busy spot on site to avoid disruption, before the cranes were transported in one piece to the lifting area.
     
    The load-in RoRo method was also changed mid-project to streamline the marshaling process. The MTC 1600s proved so efficient at lifting the monopiles, they were used to unload them from the barges instead of SPMTs. 
     
    The added benefit of this was that it significantly reduced the time needed to fully ballast each barge, as the monopiles could be lifted directly rather than their weight being transported across the deck.
     
    Thanks to a combination of the new XXL monopile handling equipment and these time-saving measures, Mammoet was able to save a lot of manual handling at critical phases and make the entire marshalling project safer and more efficient.

    Related

    Power Systems Design

    146 Charles Street
    Annapolis, Maryland 21401 USA

    Power Systems Design

    Power Systems Design is a leading global media platform serving the power electronics design engineering community. It delivers in-depth technical content, industry news, and product insights to engineers and decision-makers developing advanced power systems and technologies.

    Published 12× per year across North America and Europe, Power Systems Design is distributed through online and fully digital editions, complemented by eNewsletters, webinars, and multimedia content. The platform covers key areas including power conversion, semiconductors, renewable energy, automotive electrification, AI power systems, and industrial applications—supporting innovation across the global electronics industry.